Construction continues along Holly Ave and the surrounding area for the Holly Avenue Streetscape, Drainage and Utility Improvements.

Graves Ave, from Oak to 17/92, and S. Holly, from Albertus to Graves Ave, remain closed into May, when the project should be substantially Complete. All other roads and intersections throughout the project are opened. However, drivers, cyclists and pedestrians are urged to exercise caution as the majority of Holly Avenue is still under construction. Please be careful for areas where the road and sidewalk surfaces transition from dirt to pavement. Also, lighting will not be restored until after the project is substantially complete.

Paving began along S. Holly, E. Rose, Banana and S. Thorpe Avenue. Approximately 40% of the project is paved.

Holly Ave will be paved after paver medallion installation at the Holly and Graves intersection. The Contractor continues the reconstruction of the Holly and Graves intersection by adding new curbing, sidewalks, ADA ramps, plantings and other decorative features.

The project is approximately 80% complete and we plan to hit the 100% complete mark by the end of July.

Note – While the Contractor is still working at the time of writing, COVID-19 could change that, so please understand that these dates are subject to change.